57111

Revenge Advanced Composites

February 23, 2011Judge Ting
Denied / Government PrevailedContract Interpretation

Revenge Advanced Composites appealed a denial of its claim for additional costs related to a GPS navigation system and seating for a craft under a fixed-price incentive contract. The Board granted the government's motion for summary judgment, denying the appeal.

Material Facts

  • USSOCOM awarded a contract to RAC to build a high-speed Special Operation Forces Craft.
  • RAC submitted a certified claim for additional costs related to a GPS navigation system and seating.
  • The contracting officer denied RAC's claim, stating the contract required RAC to provide necessary systems.
  • RAC's claim was not certified as required by 41 U.S.C. § 1703(b)(1).
  • The contracting officer's decision explained that the requirements were stated in terms of performance rather than specific standards.

Parties

Appellant
Revenge Advanced Composites
Respondent Agency
United States Special Operations Command
Contract Number
Contract No. H92222-08-C-0039
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.