Muhtesem Company
Muhtesem Company appealed for damages due to the government's late payment on a contract to build a school in Iraq, claiming $149,000. The Board granted the government's motion for partial summary judgment, denying all claims.
Material Facts
- Muhtesem was awarded a firm fixed-priced contract to build a school in Iraq.
- Muhtesem billed for four progress payments and completed the contract, which was accepted by the government.
- The government paid the final installment approximately nine months after it was invoiced due to administrative errors.
- Muhtesem obtained ten commercial loans totaling approximately $356,000 before submitting its last invoice.
- A subcontractor's criminal complaint against Muhtesem led to the jailing of its president, allegedly damaging the company's reputation.
- Muhtesem claimed it was prevented from submitting offers on other projects due to non-payment of debts.
- The government denied most of Muhtesem's claim for damages, granting only a small interest penalty.
Parties
- Appellant
- Muhtesem Company
- Respondent Agency
- Department of the Army
- Contract Number
- Contract No. W91GFB-07-C-1011
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Applied Technical Systems, Inc.No. 58072March 6, 2014
- Bulova Technologies Ordnance Systems LLCNo. 57406January 28, 2014
- Stephens Construction and Concrete, Inc.No. 58670January 2, 2014
- New Iraq Ahd CompanyNo. 58800December 17, 2013
- Dace Enterprises, LLCNo. 57984November 1, 2013
- Kellogg Brown & Root Services, Inc.No. 58578September 9, 2013
Same Year
- Gray Personnel, Inc.No. 54652, 55833December 31, 2012
- ECC, InternationalNo. 55781December 28, 2012
- DODS, Inc.December 18, 2012
- Raytheon CompanyNo. 57576, 57679December 17, 2012
- TMS Envirocon, Inc.December 12, 2012
- The Public Warehousing CompanyDecember 3, 2012
Same Issue
- Africa Transport Logistics CompanyNo. 64120October 1, 2026
- Huffman Construction, LLCNo. 62591, 62783September 30, 2026
- Scot Cardillo dba Engineers Tooling SupportNo. 61612September 22, 2026
- DCS CorporationNo. 64648September 22, 2026
- VAE, Inc.No. 64437, 64464, 64465September 9, 2026
- Hensel Phelps Construction Co.No. 63316, 63397, 63398August 28, 2026