57794

Parsons Evergreene, L.L.C.

June 22, 2012Judge Clarke
DismissedLiquidated DamagesCDA Jurisdiction

Parsons Evergreene, L.L.C. appealed an alleged assessment of liquidated damages arising from delayed completion of a construction delivery order. The Board granted the government's motion and dismissed the appeal without prejudice for lack of CDA jurisdiction because the contracting officer's letter was not a final decision on a government claim.

Material Facts

  • The Air Force Materiel Command awarded master Contract No. FA8903-04-D-8703 on 12 December 2003.
  • Delivery Order 0013 was issued for design and construction of a temporary lodging facility and visiting quarters at McGuire AFB, NJ.
  • The delivery order established 27 December 2007 as the scheduled completion date.
  • The government issued a cure notice that included delays in the performance schedule among the identified deficiencies.
  • On 27 December 2007, the contracting officer stated that the temporary lodging facility was 82.1 percent complete and the visiting quarters were 73.4 percent complete.
  • The 27 December 2007 letter stated that liquidated damages would be assessed until final acceptance by the government.
  • The government took beneficial use of the facilities as of 11 September 2008, prior to completion and acceptance of the work.
  • Parsons did not submit a certified claim to the contracting officer before filing the appeal.

Parties

Appellant
Parsons Evergreene, L.L.C.
Respondent Agency
Air Force Materiel Command
Contracting Agency
Air Force Materiel Command
Contract Number
FA8903-04-D-8703
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.