Red Sea Engineers & Constructors, Inc.

April 22, 2013Judge Freeman
Partially SustainedQuantum / Damages

Red Sea Engineers & Constructors, Inc. sought reconsideration of a prior ASBCA decision regarding contract value computations and earned value assessments under Contract No. W91B4M-09-C-7340. The Board allowed the reconsideration in part, adjusting the earned value percentage but denying other claims.

Material Facts

  • Red Sea moved for reconsideration of the Board's prior decision regarding contract value computations.
  • The total contract value of the Phase 1 building construction CLINs was computed as $4,074,323.47.
  • Red Sea's computed total contract value included additional amounts for modifications that were not part of the Phase 1 work.
  • The average earned value of the Phase 1 building construction CLINs at termination was revised to 73.5 percent.
  • The issue of DBA insurance compensation was remanded to the contracting officer for determination.

Parties

Appellant
Red Sea Engineers & Constructors, Inc.
Respondent Agency
Department of the Army
Contract Number
W91B4M-09-C-7340
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.