Fluor Corporation
Fluor Corporation challenged a government claim alleging that its corporate-office Burden & Benefits allocation practices violated CAS 403 and moved to dismiss the claim as untimely under the CDA statute of limitations. The Board granted the motion as to amounts accruing before 17 November 2005 and denied it as to amounts accruing on or after that date.
Material Facts
- Fluor's business included government contracts subject to CAS.
- The CAS provisions at issue were CAS 403-40(a)(I) and CAS 403-40(b)(4).
- Fluor maintained a corporate-office Burden & Benefits indirect cost pool containing payroll taxes, health insurance, life insurance, and other employee benefits paid by the corporate office.
- The allocation base for the Burden & Benefits pool was described in Fluor's CASB Disclosure Statements as total office and field assigned salaried staff base compensation working time labor associated with Fluor domestic segments.
- Fluor's defined Base Compensation included foreign service incentives and foreign hardship allowances in addition to base salary.
- DCAA knew in August 2004 that Fluor was paying substantial hourly premium pay uplifts to employees stationed in Iraq.
- DCAA completed a CAS 403 compliance audit of Fluor's corporate-office expenses allocated to business segments on 27 September 2005.
- The ACO determined that Fluor's Burden & Benefits allocation base was not representative of the factors on which the total Burden & Benefits pool payments were based.
- The government claim covered increased costs associated with alleged CAS-noncompliant billings during fiscal years 2004 through 2010.
Parties
- Appellant
- Fluor Corporation
- Respondent Agency
- Defense Contract Management Agency
- Contract Number
- W52P1J-07-D-0008
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Phoenix Management, Inc.No. 59273April 8, 2015
- Environmental Safety Consultants, Inc.No. 58343March 2, 2015
- SureTec Insurance CompanyNo. 59343, 59647January 2, 2015
- Environmental Safety Consultants, Inc.No. 58343November 7, 2014
- Environmental Safety Consultants, Inc.No. 58343October 23, 2014
- Environmental Safety Consultants, Inc.No. 58343October 22, 2014
Same Year
- WorleyParsons International, Inc.No. 57930December 20, 2013
- TTF, L.L.C.No. 58452December 19, 2013
- Bruce E. ZoellerNo. 56578December 17, 2013
- New Iraq Ahd CompanyNo. 58800December 17, 2013
- Linc Government Services, LLCNo. 58561, 58562, 58563, 58565, 58566, 58567December 5, 2013
- The Boeing CompanyNo. 58587December 3, 2013
Same Issue
- Raytheon Company and Raytheon Missile SystemsNo. 59435, 59436, 59437, 59438, 60056, 60057, 60058, 60059, 60060, 60061May 14, 2026
- Science Applications International CorporationNo. 63509May 27, 2025
- CACI International Inc.No. 63663May 6, 2025
- Northrop Grumman CorporationNo. 62165July 5, 2023
- Honeywell International, Inc.No. 63286June 7, 2023
- General Atomics Aeronautical Systems, Inc.No. 61633, 61731February 8, 2023