61189

K&K Industries, Inc.

September 5, 2018Judge Peacock
Sustained / Appellant PrevailedDelay / Disruption / Suspension

K&K Industries, Inc. appealed the government's failure to pay the full amount claimed due to delays caused by the government under Contract No. W912HY-ll-C-0009. The Board sustained the appeal, awarding additional compensation to K&K.

Material Facts

  • The government awarded the contract in the amount of $5,648,573.58 to K&K for rehabilitation of the east and west floodgates.
  • The contract price was adjusted upward to $9,689,562.92 through modifications.
  • K&K completed the work required by the contract on the west side gates, which is not at issue in this appeal.
  • K&K's claim arises from repair work to the east gate's lower stationary hinge casting.
  • K&K discovered cracks in the casting and the government decided to use a spare casting instead.
  • K&K submitted multiple requests for information regarding the spare casting and received government approval.
  • The installation of the spare casting faced alignment issues, leading to delays.
  • K&K's claim included additional labor costs, equipment costs, and overhead due to the delays.
  • The government did not dispute the labor rates or the equipment rates claimed by K&K.
  • The contracting officer's final decision awarded $37,600 for consulting fees incurred prior to October 27, 2015.

Parties

Appellant
K&K Industries, Inc.
Respondent Agency
U.S. Army Engineer District, Galveston
Contract Number
W912HY-ll-C-0009
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.