Ken Laster Company
Ken Laster Company appealed the assessment of liquidated damages for delays in completing a contract with the Army Corps of Engineers. The Board denied the appeal, finding no excusable delays.
Material Facts
- The government awarded the 1013 Contract to Timco Blasting and Coatings, which was later modified to correct the awardee to Laster.
- The 1013 Contract incorporated FAR Clause 52.211-12, requiring Laster to pay liquidated damages for failure to complete work on time.
- Task Order No. 0003 required work to be completed 158 calendar days after Laster received the notice to proceed.
- Laster received the notice to proceed on or about March 11, 2010, with an original completion date of August 16, 2010.
- The parties extended the due date to May 22, 2011, but Laster substantially completed work on March 5, 2012, 289 days late.
- The government assessed $91,035 in liquidated damages due to the completion date being 289 days late.
Parties
- Appellant
- Ken Laster Company
- Respondent Agency
- U.S. Army Engineer District, Tulsa
- Contract Number
- W912BV-09-D-1013
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Procal Electric, Inc.No. 63580-ADROctober 2, 2026
- VESEQU LLCNo. 64468August 21, 2026
- PDO Ahuska Joint Venture LLCNo. 64164July 13, 2026
- First Street Contractors, LLCNo. 64028June 10, 2026
- VESEQU LLCNo. 64468May 21, 2026
- First Street Contractors, LLCNo. 64028February 20, 2026
Same Year
- Sweet Star Logistic ServiceNo. 62082December 29, 2020
- Nan, Inc.No. 61472, 61482, 61500, 61509, 61514, 61523, 61555, 61569, 61705, 61726, 61727, 61728, 61821, 61822, 61823, 61963December 18, 2020
- Asahi General Trading & Cont. Co. W.L.L.No. 62445December 18, 2020
- Kautaq Construction Services, LLCNo. 62462-ADRDecember 18, 2020
- MAC Electric Inc.No. 62503December 18, 2020
- Parsons Government Services, Inc.No. 62112December 17, 2020
Same Issue
- Hensel Phelps Construction Co.No. 63316, 63397, 63398August 28, 2026
- J.A.M. Construction Services, Inc.No. 63378, 64226, 64439July 28, 2026
- ACC Construction Co., Inc.No. 63528, 64067July 16, 2026
- Healtheon, Inc.No. 63145July 24, 2025
- Gideon Contracting, LLCNo. 63561May 12, 2025
- ECC International Constructors, LLCNo. 59586April 18, 2025