Nauset Construction Corporation
Nauset Construction Corporation appealed the deemed denial of two claims and a termination for default by the Department of the Army. The Board asserted jurisdiction over the claims but dismissed the appeal of the termination for default as untimely.
Material Facts
- Nauset Construction Corporation was awarded a contract by the National Guard Bureau on November 1, 2013, for $20,521,858.00.
- Nauset submitted a certified claim (Claim 1) to the contracting officer on May 12, 2017, for $2,563,622 plus an extension of time.
- The contracting officer informed Nauset on July 10, 2017, that she could not render a decision within the required 60 days due to ongoing investigations.
- The contracting officer terminated the contract for default on November 17, 2017.
- Nauset submitted a second certified claim (Claim 2) on February 12, 2018, demanding payment for costs incurred and asserting wrongful termination.
- Nauset appealed to the Board on June 27, 2018, after the contracting officer failed to issue a decision on the claims.
Parties
- Appellant
- Nauset Construction Corporation
- Respondent Agency
- Department of the Army
- Contract Number
- W912SV-13-C-0007
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Left Hand Design CorporationNo. 62458November 7, 2024
- Vectrus Systems CorporationNo. 63465May 22, 2024
- MECTS Services Joint VentureNo. 63441July 19, 2023
- Vectrus Systems CorporationNo. 61651February 6, 2023
- Derian, Inc.No. 63283February 1, 2023
- Mills Design Group Construction and DevelopmentNo. 62432February 1, 2023
Same Year
- Cellular Materials International, Inc.No. 61408December 27, 2021
- Meltech Corporation, Inc.No. 61706, 61768December 17, 2021
- Telos CorporationNo. 62950December 16, 2021
- General Dynamics Mission Systems, Inc.No. 62180-ADRDecember 13, 2021
- Adjuvant/Capital, LLCNo. 62760December 13, 2021
- Veteran Facility Services, LLCNo. 61855, 61983, 62386December 9, 2021
Same Issue
- Huffman Construction, LLCNo. 62591, 62783September 30, 2026
- VAE, Inc.No. 64437, 64464, 64465September 9, 2026
- Hensel Phelps Construction Co.No. 63316, 63397, 63398August 28, 2026
- Erik Robinson d/b/a The Artwork FactoryNo. 63727, 63809August 19, 2026
- U.S. Aeroteam, Inc.No. 61972, 61973August 6, 2026
- Cardinal Contracting Co., LLCNo. 62872July 30, 2026