62872

Cardinal Contracting Co., LLC

July 30, 2026Judge Herzfeld
Partially SustainedDelay / Disruption / SuspensionContract InterpretationQuantum / DamagesAuthority of Government Agents

Cardinal Contracting Co., LLC challenged the Air Force's alleged failure to permit retrieval of equipment during COVID-19 base restrictions and its delay in allowing Cardinal to restart performance after being deemed mission essential. The Board rejected the equipment-access breach claim, sustained entitlement to delay damages from May 21, 2020, through June 12, 2020, and remanded for determination of quantum.

Material Facts

  • Cardinal and the Air Force entered an indefinite delivery/indefinite quantity contract for construction and repair of asphalt, including milling and paving.
  • The Air Force issued a task order for Cardinal to repave two parking lots at Joint Base McGuire-Dix-Lakehurst, New Jersey, with a one-year performance period through September 29, 2020.
  • Cardinal had mobilized paving equipment at the base when the installation commander declared a COVID-19 public health emergency.
  • The contracting officer suspended Cardinal's performance, designated Cardinal non-mission essential, and directed it to refrain from being physically present on base.
  • An emergency access policy would have permitted Cardinal to retrieve its idle paving equipment, but the contracting officer and contracting officer's representative did not know about that policy.
  • Cardinal's April 7 entry authority list submission stated that it sought to renew passes to continue performing the contract and did not state that it sought access to retrieve idle equipment.
  • On May 21, the Air Force deemed Cardinal mission essential and directed it to continue performing.
  • Cardinal's April 7 entry authority list remained in effect under the contract until Cardinal submitted a new entry authority list.
  • Cardinal submitted a new entry authority list on June 3 and learned on June 12 that it had access to the work site, materials, and equipment.
  • Cardinal did not restart performance until June 26 and attributed the additional delay to maintenance required for equipment that had remained idle.
  • Cardinal completed the task-order work on September 15, 2020, within the original completion period.

Parties

Appellant
Cardinal Contracting Co., LLC
Respondent Agency
Department of the Air Force
Contracting Agency
Air Force
Contract Number
FA4484-14-D-0004
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.