6256162640

Pangea, Inc.

January 4, 2022Judge McIlmail
Partially SustainedQuantum / DamagesDelay / Disruption / SuspensionCPARS / Past-Performance Evaluation

Pangea, Inc. appealed several claims against the U.S. Army Corps of Engineers regarding a construction contract, resulting in a mixed outcome on cross-motions for summary judgment.

Material Facts

  • On September 28, 2017, the U.S. Army Corps of Engineers contracted for Pangea, Inc. to design and construct a pre-engineered metal building warehouse for $3,696,859.
  • The scheduled period of performance was 365 calendar days after notice to proceed, with a completion date of October 24, 2018.
  • Pangea submitted a Request for Contracting Officer’s Final Decision on a multi-issue, certified claim on October 17, 2019, requesting compensation of $983,067.73 and a time extension of 169 calendar days.
  • The claim was a request for reconsideration of the denial of six previously filed Requests for Equitable Adjustment (REA) and a previously issued Final Contractor Performance Assessment Reporting System (CPARS) Evaluation.
  • The government issued final decisions addressing the issues raised in REAs 2, 4, 6, and the Final CPARS Evaluation in March and August 2020.

Parties

Appellant
Pangea, Inc.
Respondent Agency
U.S. Army Corps of Engineers
Contract Number
Contract No. W912WR-17-C-0039
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.