The Army Corps of Engineers moved to dismiss Kellogg Brown & Root Services, Inc.'s appeals concerning liquidated damages and recoupment of provisional payments as untimely. The Board denied the motion, holding that KBR timely appealed the contracting officer's final decision and that the subsequent demand letters constituted valid government claims and final decisions.

Material Facts

  • The Army Corps of Engineers and KBR executed Contract No. W912GB-13-C-0011 for construction of an Aegis Ashore Missile Defense System site at Deveselu Air Base in Romania.
  • The contract was for a firm, fixed-price amount and included milestone dates, a September 2015 completion deadline, and liquidated-damages provisions.
  • Modification No. P00007 accelerated efforts, increased contract funding, and described the new payments as provisional and contingent on KBR demonstrating excusable delays.
  • The Army Corps of Engineers added a total of $27 million to the contract funding through later modifications.
  • KBR substantially completed the project on December 19, 2015.
  • KBR's certified claim sought a time extension and compensation based on alleged government delays, constructive and written changes, and accelerated performance.
  • The July 1, 2020 contracting officer's decision denied KBR's certified claim, stated that provisional payments were subject to recoupment or offset, and reserved the right to collect liquidated damages in a future decision.
  • The July 1, 2020 decision did not state a dollar figure for liquidated damages owed.
  • The December 10, 2020 demand letters sought repayment of provisional acceleration payments and liquidated damages.
  • The liquidated-damages demand letter asserted that KBR owed $6,398,210 and that $2,421,685 would be offset from unpaid contract amounts.
  • Neither demand letter included notice of CDA appeal rights.
  • KBR timely appealed both demand letters and requested deferral of collection pending resolution of its Board appeal.

Parties

Appellant
Kellogg Brown & Root Services, Inc.
Respondent Agency
United States Army Corps of Engineers
Contracting Agency
Army Corps of Engineers
Contract Number
W912GB-13-C-0011
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.