Sustained / Appellant PrevailedDelay / Disruption / Suspension

Al Ghanim Combined Group W.L.L. appealed for delay costs from the United States Army Corps of Engineers due to delays in obtaining security escorts for construction work in Kuwait. The Board sustained the appeal, awarding Al Ghanim $34,320.11 plus interest.

Material Facts

  • The Army Corps awarded Al Ghanim an indefinite delivery/indefinite quantity job order contract on November 7, 2013.
  • Al Ghanim was tasked with construction work at Camp Ali Al Salem, Kuwait, requiring security escorts as per Air Force regulations.
  • Delays occurred due to the late arrival of security escorts, impacting Al Ghanim's ability to commence work on time.
  • Al Ghanim submitted requests for equitable adjustment seeking time extensions and costs for delays from January to October 2018.
  • The contracting officer recognized some delays but denied any cost adjustments, stating they were non-compensable.

Parties

Appellant
Al Ghanim Combined Group W.L.L.
Respondent Agency
United States Army Corps of Engineers
Contract Number
W912ER-14-D-0005
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.