McCarthy HITT - Next NGA West JV
McCarthy HITT - Next NGA West JV appealed the denial of claims related to delays and disruptions caused by government actions during the COVID-19 pandemic. The Board denied the government's motion to dismiss the appeals.
Material Facts
- McCarthy-HITT was awarded a design-build contract by USACE for the NGA's Next NGA West Campus Project.
- The contract was a DO-C2 rated order certified for national defense.
- McCarthy-HITT entered into subcontracts with three subcontractors: icon Mechanical Construction and Engineering, Sachs Electric Company, and W. James Taylor, Inc.
- The subcontract prices were based on assumptions regarding material costs and normal working conditions.
- By March 20, 2020, McCarthy-HITT determined that the COVID-19 pandemic would significantly impact performance.
- McCarthy-HITT notified USACE of potential impacts and requested collaboration to manage delays.
- USACE failed to provide timely extensions or adjustments to the contract price.
- McCarthy-HITT submitted certified claims to USACE seeking equitable adjustments totaling $23,513,080.57, which were denied.
Parties
- Appellant
- McCarthy HITT - Next NGA West JV
- Respondent Agency
- U.S. Army Corps of Engineers
- Contract Number
- Contract No. W912DQ-19-C-7001
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Africa Transport Logistics CompanyNo. 64120October 1, 2026
- Environet, Inc.No. 64167September 23, 2026
- Hensel Phelps Construction CompanyNo. 64327September 14, 2026
- Marine Hydraulics International, LLCNo. 63429, 63511August 6, 2026
- Vision Distributors LLCNo. 64357July 17, 2026
- KUNJ Construction CorporationNo. 63240June 12, 2026
Same Year
- Central Environmental, Inc.No. 62628December 28, 2023
- Horizon Environmental Services, Inc.No. 63428, 63463December 28, 2023
- O-Tech Solutions, LLCNo. 61898-EAJA, 62095-EAJADecember 26, 2023
- PAE Applied Technologies LLCNo. 63233December 26, 2023
- G-W Management Services, LLCNo. 63318December 26, 2023
- SOC LLCNo. 63660December 22, 2023
Same Issue
- Africa Transport Logistics CompanyNo. 64120October 1, 2026
- Martin Brothers ConstructionNo. 63196, 63431September 30, 2026
- Vigor Marine, LLCNo. 63405September 24, 2026
- Hensel Phelps Construction CompanyNo. 64327September 14, 2026
- WSP USA Solutions Inc.No. 62674September 1, 2026
- Hensel Phelps Construction Co.No. 63316, 63397, 63398August 28, 2026