McCarthy HITT - Next NGA West JV

December 20, 2023Judge McLish
Denied / Government PrevailedContract Changes / Constructive ChangesDelay / Disruption / Suspension

McCarthy HITT - Next NGA West JV appealed the denial of claims related to delays and disruptions caused by government actions during the COVID-19 pandemic. The Board denied the government's motion to dismiss the appeals.

Material Facts

  • McCarthy-HITT was awarded a design-build contract by USACE for the NGA's Next NGA West Campus Project.
  • The contract was a DO-C2 rated order certified for national defense.
  • McCarthy-HITT entered into subcontracts with three subcontractors: icon Mechanical Construction and Engineering, Sachs Electric Company, and W. James Taylor, Inc.
  • The subcontract prices were based on assumptions regarding material costs and normal working conditions.
  • By March 20, 2020, McCarthy-HITT determined that the COVID-19 pandemic would significantly impact performance.
  • McCarthy-HITT notified USACE of potential impacts and requested collaboration to manage delays.
  • USACE failed to provide timely extensions or adjustments to the contract price.
  • McCarthy-HITT submitted certified claims to USACE seeking equitable adjustments totaling $23,513,080.57, which were denied.

Parties

Appellant
McCarthy HITT - Next NGA West JV
Respondent Agency
U.S. Army Corps of Engineers
Contract Number
Contract No. W912DQ-19-C-7001
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.