Connectec Company, Inc.
Connectec Company, Inc. appealed the contracting officer's decision to terminate a purchase order for default. The Board dismissed the appeal for lack of jurisdiction.
Material Facts
- The Defense Supply Center Philadelphia issued Purchase Order No. SPM5L4-09-M-I018 to Connectec for 3500 levers.
- The purchase order did not require Connectec to sign it and did not include a termination for default clause.
- Connectec's first production lot of levers was completed in September 2009, but the samples failed product verification testing.
- The government issued unilateral modifications extending delivery dates and allowing for retests, but subsequent samples continued to fail.
- On 4 February 2011, the contracting officer notified Connectec that its levers failed product verification testing and that the unilateral order would be withdrawn.
- Connectec appealed the contracting officer's decision to terminate the contract for default on 1 March 2011.
Parties
- Appellant
- Connectec Company, Inc.
- Contract Number
- SPM5L4-09-M-I018
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Metal Trades, Inc.No. 62966November 2, 2021
- Powertronic Systems Florida, Inc.No. 62174October 19, 2021
- Huffman Construction, LLCNo. 62591, 62783August 5, 2021
- U.S. Pan American Solutions, LLCNo. 62629August 5, 2021
- URS Federal Support Services, Inc.No. 59998-QUANAugust 3, 2021
- G&S Carpet Mills, Inc.No. 62799June 25, 2021
Same Year
- Joint Venture Makyal Ins. Ve Tic. A.S. & Mehmet Erdal Kamisli Co. Ltd.No. 56956December 28, 2011
- Distributed Solutions, Inc.No. 57266December 28, 2011
- Quimba Software, Inc.No. 57636December 19, 2011
- American General Trading & Contracting, WLLNo. 56758December 13, 2011
- Harry RichardsonNo. 57582December 9, 2011
- Sharp Electronics CorporationNo. 57583December 6, 2011
Same Issue
- Scot Cardillo dba Engineers Tooling SupportNo. 61612September 22, 2026
- Wild Hare Haulers, LLCNo. 64596, 64597, 64598September 15, 2026
- Hensel Phelps Construction CompanyNo. 64327September 14, 2026
- Bahadir Construction Engineering Contracting & Trading Inc. Co. and Impreza Costruzioni Giuseppe Maltauro S.p. A Joint VentureNo. 64038, 64336, 64428September 9, 2026
- VAE, Inc.No. 64437, 64464, 64465September 9, 2026
- Dubai Pearl CompanyNo. 64444August 26, 2026