New Era Contract Sales, Inc.
New Era Contract Sales, Inc. appealed the termination for default of three delivery orders for fuel pumps issued under an indefinite quantity contract. The Board granted the government's motion for summary judgment, denying the appeals.
Material Facts
- New Era Contract Sales, Inc. was awarded an indefinite quantity Basic Contract No. SPM750-06-D-746I for fuel pumps.
- The government terminated three delivery orders for default due to New Era's failure to deliver the parts ordered.
- New Era claimed its failure to deliver was excused because its subcontractor refused to honor previously quoted prices.
- The contract was a firm fixed-price contract without an economic price adjustment provision.
- New Era's subcontractor would not honor the prices due to a change in the discount structure from the manufacturer, Isuzu Motors.
- The government issued a Show Cause notice to New Era after the delivery dates had passed without performance.
- The government terminated the delivery orders citing FAR 52.249-8, which outlines conditions for default termination.
Parties
- Appellant
- New Era Contract Sales, Inc.
- Contract Number
- SPM750-06-D-746I
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Kelly-Ryan, Inc.No. 57168December 5, 2017
- Optimum Services, Inc.No. 58755, 59952July 20, 2017
- Raytheon Company and Raytheon Missile SystemsNo. 61191, 61192, 61193June 6, 2017
- Raytheon CompanyNo. 58849May 2, 2017
- Swinerton Builders NorthwestNo. 57329April 24, 2017
- General Atomics Aeronautical Systems, Inc.No. 60002, 60003March 24, 2017
Same Year
- Joint Venture Makyal Ins. Ve Tic. A.S. & Mehmet Erdal Kamisli Co. Ltd.No. 56956December 28, 2011
- Distributed Solutions, Inc.No. 57266December 28, 2011
- Quimba Software, Inc.No. 57636December 19, 2011
- American General Trading & Contracting, WLLNo. 56758December 13, 2011
- Harry RichardsonNo. 57582December 9, 2011
- Sharp Electronics CorporationNo. 57583December 6, 2011
Same Issue
- Huffman Construction, LLCNo. 62591, 62783September 30, 2026
- US Military CorpNo. 64321September 24, 2026
- Relyant Global LLCNo. 64032, 64111, 64230, 64231, 64517August 24, 2026
- Visionary Construction, Inc. dba Visionary ServicesNo. 64426August 20, 2026
- Peritia LLCNo. 64495, 64586August 20, 2026
- J.A.M. Construction Services, Inc.No. 63378, 64226, 64439July 28, 2026