57594

Raytheon Missile Systems

October 11, 2011Judge Clarke
Sustained / Appellant PrevailedContract Changes / Constructive ChangesDelay / Disruption / Suspension

Raytheon Missile Systems appealed the denial of a claim arising from increased JP-10 fuel costs under a firm-fixed-price Navy contract. The Board denied the Navy's motion for summary judgment because disputed material facts concerned the relationship between the Navy and DLA-Energy, the source of the fuel-price increase, and potential constructive change and non-interference theories.

Material Facts

  • Contract No. N00019-04-C-0569 was a firm-fixed-price contract.
  • The contract did not contain an economic price adjustment clause.
  • Raytheon was required to use JP-10 fuel in performing the contract.
  • DLA-Energy was identified as the sole source of JP-10 fuel available to Raytheon.
  • Raytheon experienced a nearly 80% JP-10 price increase in fiscal years 2007 through 2010.
  • Raytheon attributed the price increase to a DLA-Energy corporate decision to construct a Defense Fuels Support Point specifically for JP-10, financed by an increase in the price of JP-10.
  • Raytheon asserted that construction of the Defense Fuels Support Point supported NAVAIR's programs.

Parties

Appellant
Raytheon Missile Systems
Respondent Agency
Navy
Contracting Agency
Naval Air Systems Command (NAVAIR)
Contract Number
N00019-04-C-0569
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.