5754957563

The Boeing Company

September 6, 2013Judge Freeman
Sustained / Appellant PrevailedCost Accounting Standards (CAS)DCAA InvolvedDCMA InvolvedCAS at Issue

The Boeing Company appealed contracting officer decisions holding it liable for increased costs resulting from unilateral, simultaneous changes in cost accounting practices at two business segments. The Board sustained the appeals on entitlement, holding that Boeing could combine the simultaneous changes for aggregate cost-impact purposes under the pre-April 8, 2005 statutory, regulatory, and agency-guidance framework, and remanded quantum for settlement.

Material Facts

  • Boeing implemented three unilateral financially significant changes to its established cost accounting practices at its Philadelphia segment effective January 1, 2005.
  • Boeing implemented six unilateral financially significant changes to its established cost accounting practices at its El Segundo segment effective January 1, 2005.
  • The changes at both segments were documented in revised CASB Disclosure Statements.
  • The cost impacts were calculated on affected CAS-covered contracts and subcontracts at each segment.
  • All contracts and subcontracts used to calculate the impacts included the FAR 52.230-2 Cost Accounting Standards clause.
  • All contracts and subcontracts used to calculate the impacts were entered into before January 1, 2005.
  • Before April 8, 2005, DCMC and DCAA manuals stated that several accounting changes within a segment could be combined for offset purposes if they had the same effective date.
  • FAR Part 30 was amended effective April 8, 2005, to add Section 30.606 addressing resolution of cost impacts.
  • The Philadelphia contracting officer's November 3, 2010 memorandum stated that pre-2005 practice was to consider and net all accounting changes together in determining whether the government paid increased costs in the aggregate.
  • The Philadelphia contracting officer issued a final decision dated December 9, 2010, and the El Segundo contracting officer issued a final decision dated December 14, 2010.

Parties

Appellant
The Boeing Company
Respondent Agency
Defense Contract Management Agency
Contracting Agency
Defense Contract Management Agency
Contract Number
W911 W6-05-2-0006; FA8808-04-C-0022
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.