ECC International, LLC

November 16, 2018Judge Woodrow
Denied / Government PrevailedContract Interpretation

ECC International, LLC appealed a decision regarding its claim for costs due to the closure of the Friendship Gate, an access route to its construction site in Afghanistan. The Board denied the appeal, ruling that the contractor bore the risk of changes to base access requirements.

Material Facts

  • ECCI was awarded Contract No. W5J9LE-11-C-0045 for construction at Camp Shorab, Afghanistan.
  • The contract required ECCI to comply with security and access procedures in a wartime environment.
  • The Friendship Gate was used by ECCI for access to the project site until its closure by the U.S. Marine Corps in December 2012.
  • ECCI claimed 28 days of compensable delay and $1,652,958 in costs due to the closure of the Friendship Gate.
  • The contracting officer denied ECCI's REA, stating the closure was a decision made by the U.S. Marines and not by USACE.

Parties

Appellant
ECC International, LLC
Respondent Agency
U.S. Army Corps of Engineers
Contract Number
W5J9LE-11-C-0045
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.