Jaxon Construction, Inc.
Jaxon Construction, Inc. appealed the contracting officer's decision to terminate its roof-repair contract for default, seeking conversion to a termination for convenience. The Board sustained the appeal, finding the government did not prove that the default termination was justified.
Material Facts
- The contract was awarded to Jaxon Construction, Inc. on August 22, 2025, for $438,765.
- The contract required performance within 80 working days after the Notice to Proceed.
- The Notice to Proceed was executed on September 18, 2025.
- Jaxon missed the deadline for the practicable schedule and Quality Control Plan due on October 3.
- The contracting officer issued a cure notice on November 19, citing failure to make progress.
- The contracting officer terminated the contract for default on December 22, 2025.
- Jaxon did not perform any physical roofing work before termination.
- The government found Jaxon's December 3 submissions deficient.
- The contracting officer did not communicate deficiencies before termination.
Parties
- Appellant
- Jaxon Construction, Inc.
- Respondent Agency
- Department of the Army
- Contract Number
- W519TC-25-C-A037
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Arctic Swan Construction Inc.No. 64085September 22, 2026
- WSP USA Solutions Inc.No. 62674September 1, 2026
- Arctic Swan Construction Inc.No. 63510, 64085June 16, 2026
- Eleven Bravo Group, LLCNo. 63932April 8, 2026
- Penna Group, LLCNo. 61708-ADR, 61641-ADR, 61642-ADRFebruary 20, 2026
- InfiniSource Consulting Solutions, Inc.No. 64354, 64355February 19, 2026
Same Year
- Bodell Construction CompanyNo. 63517-ADR, 63850-ADROctober 2, 2026
- Procal Electric, Inc.No. 63580-ADROctober 2, 2026
- Africa Transport Logistics CompanyNo. 64120October 1, 2026
- Kearfott CorporationNo. 64328October 1, 2026
- Relyant Global, LLCNo. 64606October 1, 2026
- Relyant Global, LLCNo. 64651October 1, 2026
Same Issue
- Huffman Construction, LLCNo. 62591, 62783September 30, 2026
- US Military CorpNo. 64321September 24, 2026
- Relyant Global LLCNo. 64032, 64111, 64230, 64231, 64517August 24, 2026
- Visionary Construction, Inc. dba Visionary ServicesNo. 64426August 20, 2026
- Peritia LLCNo. 64495, 64586August 20, 2026
- J.A.M. Construction Services, Inc.No. 63378, 64226, 64439July 28, 2026