6068660687

K-Con, Inc.

January 12, 2017Judge Woodrow
Denied / Government PrevailedContract Interpretation

K-Con, Inc. appealed for a total of $116,336.56 due to increased costs from delays in contract performance. The Board concluded that bonding requirements were incorporated into the contracts by operation of law.

Material Facts

  • K-Con, Inc. was awarded two firm-fixed-price contracts for construction projects.
  • The contracts were for the construction of a laundry facility and a communications equipment shelter.
  • The government requested performance and payment bonds after awarding the contracts but before issuing a notice to proceed.
  • K-Con was unable to provide the required bonding and proposed a tripartite agreement, which the government rejected.
  • K-Con eventually provided the required bonding nearly two years later, leading to a modification of the contracts to increase costs.

Parties

Appellant
K-Con, Inc.
Respondent Agency
Department of the Army
Contract Number
W912SV-13-F-0100, W912SV-13-F-0121
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.