Skanska USA Building, Inc.
Skanska USA Building, Inc. appealed against the U.S. Army Corps of Engineers regarding delays caused by the government's untimely approval of steel shop drawings, claiming constructive acceleration. The Board granted the government's motion for summary judgment, concluding that Skanska failed to timely request an extension.
Material Facts
- The government awarded fixed-priced Contract No. W912DR-13-C-0002 to Skanska for the construction of the Asymmetric Warfare Group Headquarters Complex.
- Skanska was required to submit shop drawings to the government for approval before beginning fabrication.
- The government failed to return the shop drawing submittals within the required 30-day period.
- Skanska notified the government multiple times about delays caused by the late return of submittals but did not formally request an extension of time.
- Skanska's change order request included zero additional days to the project schedule.
Parties
- Appellant
- Skanska USA Building, Inc.
- Respondent Agency
- U.S. Army Corps of Engineers
- Contract Number
- Contract No. W912DR-13-C-0002
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Martin Brothers ConstructionNo. 63196, 63431September 30, 2026
- Vigor Marine, LLCNo. 63405September 24, 2026
- KiewitPhelpsNo. 61184, 62119, 62980, 64137September 1, 2026
- Hydraulic International, Inc.No. 64332August 17, 2026
- Blackstone Consulting, Inc.No. 64558July 30, 2026
- Potomac Yard ContractorsNo. 63032July 7, 2026
Same Year
- Cellular Materials International, Inc.No. 61408December 27, 2021
- Meltech Corporation, Inc.No. 61706, 61768December 17, 2021
- Telos CorporationNo. 62950December 16, 2021
- General Dynamics Mission Systems, Inc.No. 62180-ADRDecember 13, 2021
- Adjuvant/Capital, LLCNo. 62760December 13, 2021
- Veteran Facility Services, LLCNo. 61855, 61983, 62386December 9, 2021
Same Issue
- Huffman Construction, LLCNo. 62591, 62783September 30, 2026
- Scot Cardillo dba Engineers Tooling SupportNo. 61612September 22, 2026
- Hensel Phelps Construction CompanyNo. 64327September 14, 2026
- Hensel Phelps Construction Co.No. 63316, 63397, 63398August 28, 2026
- Relyant Global LLCNo. 64032, 64111, 64230, 64231, 64517August 24, 2026
- Marine Hydraulics International, LLCNo. 63429, 63511August 6, 2026