March 13, 2023Judge Herzfeld
Denied / Government PrevailedEquitable Adjustment (REA)Accord & Satisfaction / Release / Waiver

Frazier Investments, Inc. d/b/a Optimum Construction appealed for an equitable adjustment due to alleged constructive changes by the Air Force during contract performance, which the Board denied.

Material Facts

  • The Air Force awarded contract No. FA2823-16-C-4036 to Optimum for $1,946,339.52 to replace the fire alarm control panel and fire suppression system.
  • The Air Force issued a notice to proceed on November 1, 2016, and informed Optimum that work would need to occur during nights and weekends.
  • Optimum proposed additional costs for changes in work requirements, which were negotiated with the Air Force.
  • The parties signed Modification No. P00001, which stated it was based on mutual agreement and constituted full satisfaction of rights to equitable adjustment.
  • Optimum later submitted a claim seeking $98,695, including costs from its subcontractor Pugh.

Parties

Appellant
Frazier Investments, Inc. d/b/a Optimum Construction
Respondent Agency
Department of the Air Force
Contract Number
FA2823-16-C-4036
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.