63093

Patricia I. Romero, Inc. d/b/a Pacific West Builders

May 12, 2023Judge McLish
Partially SustainedQuantum / DamagesStatute of Limitations / TimelinessCDA JurisdictionAccord & Satisfaction / Release / Waiver

Patricia I. Romero, Inc. d/b/a Pacific West Builders appealed a decision regarding claims for additional work and delays under a task order issued by NAVFAC. The Board granted summary judgment in favor of the government on most claims, citing statute of limitations and other defenses.

Material Facts

  • The contract at issue is a task order under an indefinite-delivery, indefinite-quantity construction contract awarded to PWB.
  • The task order was awarded on or about September 20, 2011, for the Denver NOSC Repair Project at Buckley Air Force Base.
  • PWB's certified claim included allegations of delays and additional costs due to NAVFAC's actions.
  • The contracting officer issued a final decision on PWB's claim on September 13, 2021, granting it in part and denying it in part.
  • PWB filed this appeal on December 7, 2021, seeking relief for additional work and delay costs.

Parties

Appellant
Patricia I. Romero, Inc. d/b/a Pacific West Builders
Respondent Agency
Naval Facilities Engineering Systems Command Southwest
Contract Number
Contract No. N62473-08-D-8655
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.