Pontchartrain Partners, LLC appealed a decision regarding claims for equitable adjustment and time extension related to a U.S. Army Corps of Engineers construction project, which the Board partially denied.

Material Facts

  • The Corps awarded Contract No. W912HY-19-C-0016 to Pontchartrain in September 2019.
  • Pontchartrain submitted Request for Information (RFI) 0005 in April 2020 regarding excessive erosion.
  • The Corps issued two bilateral modifications to address the erosion issues.
  • Modification P00001 established a not-to-exceed amount of $500,000 and granted 30 additional days.
  • Modification P00002 awarded $409,322.04 and 34 additional days.
  • Pontchartrain submitted a certified claim in December 2022 asserting various amounts for work associated with the modifications.
  • The contracting officer denied Pontchartrain's claims related to Modifications P00001 and P00002.

Parties

Appellant
Pontchartrain Partners, LLC
Respondent Agency
U.S. Army Corps of Engineers
Contracting Agency
U.S. Army Engineer District, Galveston
Contract Number
Contract No. W912HY-19-C-0016
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.