Raytheon Company, Space & Airborne Systems

April 22, 2013Judge Grant
Partially SustainedCost Accounting Standards (CAS)Statute of Limitations / TimelinessCDA JurisdictionDCAA InvolvedDCMA InvolvedCAS at Issue

Raytheon Company, Space & Airborne Systems moved to dismiss the government's claims concerning accounting-practice changes for lack of jurisdiction under the Contract Disputes Act's six-year statute of limitations. The Board denied dismissal of the Revision 1 property-accounting/property-management claim but granted dismissal of the Revision 3 ERP and Revision 4 claims as untimely.

Material Facts

  • Raytheon was awarded Contract No. F04701-03-C-0008 on 21 February 2003.
  • The contract contained FAR clause 52.230-2 and FAR clause 52.230-6 concerning accounting-practice changes, CAS disclosure statements, cost adjustments, and general dollar magnitude reporting.
  • Revision 1 included a property-accounting/property-management change effective 1 January 2004.
  • Raytheon did not provide cost-impact information concerning the Revision 1 property-accounting/property-management change until 3 April 2006.
  • Revision 3 included an ERP accounting change that Raytheon reported would be effective 1 January 2005 and would affect allocations to flexibly priced and FFP contracts.
  • Revision 4 Change 6 concerned an accommodation fringe rate and was to be effective 24 January 2005.
  • Revision 4 Change 11 concerned inter-organizational transfers and had gone into effect 1 January 2004.
  • Revision 4 Change 5 concerned labor-rate calculations and was to be effective 24 January 2005.
  • DCAA issued audit or related memoranda concerning Revision 1, Revision 3, and outstanding Raytheon audit matters.
  • DCMA issued final decisions in 2011 asserting claims for alleged increased costs and compound interest arising from the accounting changes.

Parties

Appellant
Raytheon Company, Space & Airborne Systems
Respondent Agency
Defense Contract Management Agency
Contracting Agency
Defense Contract Management Agency
Contract Number
F04701-03-C-0008
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.