Contrack International, Inc.
Contrack International, Inc. appealed a denial of compensation for delays caused by vehicles owned by the Afghan National Army on a construction project in Afghanistan. The Board denied the appellant's motion for summary judgment.
Material Facts
- The U.S. Army Corps of Engineers awarded Contrack a contract for the design and construction of facilities for the Afghan National Army in Zabul Province, Afghanistan.
- The contract required performance within 540 days and incorporated FAR 52.236-3, SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK.
- Contrack experienced a 52-day delay due to vehicles owned by the Afghan National Army occupying the work area.
- The contracting officer issued Modification No. P00006, extending the performance period by 52 days but providing no additional compensation.
- There is a material dispute regarding the government's authority to move the vehicles, with the government asserting it lacked the authority, equipment, and manpower.
Parties
- Appellant
- Contrack International, Inc.
- Respondent Agency
- U.S. Army Engineer District, Middle East
- Contract Number
- W5J9LE-12-C-0017
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Korte Construction CompanyNo. 63539, 63540September 30, 2026
- Dubai Pearl CompanyNo. 64444August 26, 2026
- U.S. Aeroteam, Inc.No. 61972, 61973August 6, 2026
- J. Star Enterprises, Inc.No. 63627, 63647, 63656, 63657, 63658June 10, 2026
- J. Star Enterprises, Inc.No. 63603June 9, 2026
- Vectrus Systems CorporationNo. 63420May 11, 2026
Same Year
- Sparton DeLeon Springs, LLCNo. 60416December 28, 2016
- Kellogg Brown & Root Services, Inc.No. 59873, 60885December 21, 2016
- Lockheed Martin Integrated Systems, Inc.No. 59508, 59509December 20, 2016
- CDM Constructors, Inc.No. 59524December 20, 2016
- Astro Systems, Inc.No. 60769, 60781December 20, 2016
- First Division Design, LLCNo. 60884-975December 15, 2016
Same Issue
- Huffman Construction, LLCNo. 62591, 62783September 30, 2026
- Scot Cardillo dba Engineers Tooling SupportNo. 61612September 22, 2026
- Hensel Phelps Construction CompanyNo. 64327September 14, 2026
- Hensel Phelps Construction Co.No. 63316, 63397, 63398August 28, 2026
- Relyant Global LLCNo. 64032, 64111, 64230, 64231, 64517August 24, 2026
- Marine Hydraulics International, LLCNo. 63429, 63511August 6, 2026