6094861166

American International Contractors, Inc.

May 29, 2018Judge O'Connell
Partially SustainedLiquidated Damages

American International Contractors, Inc. appealed the government's withholding of liquidated damages under Contract No. W912ER-14-C-0002, resulting in a mixed outcome on the parties' cross-motions for summary judgment.

Material Facts

  • On 21 January 2014, the U.S. Army Corps of Engineers and American International Contractors, Inc. entered into a contract for a project at a price of $9,788,000.
  • The contract required AICI to complete the HQ facility by 7 March 2015 and the FSU/FLS facility by 6 April 2015.
  • The contract contained a liquidated damages clause providing for $2,447.00 per day for delays.
  • AICI did not complete the original contract work on time, leading to the government withholding $159,055 in liquidated damages.
  • AICI submitted an uncertified claim to the contracting officer seeking the return of the liquidated damages.
  • The contracting officer issued a final decision rejecting AICI's main argument but ordered the release of $31,811 in liquidated damages.

Parties

Appellant
American International Contractors, Inc.
Respondent Agency
U.S. Army Engineer District, Middle East
Contract Number
W912ER-14-C-0002
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.