Blanchard's Contracting, LLC appealed a decision regarding claims for delays and additional work under a design-build contract. The Board dismissed certain claims for lack of jurisdiction.

Material Facts

  • The parties entered into a design-build contract in the amount of $523,513.60 on June 25, 2019.
  • Blanchard submitted a claim to the contracting officer on April 17, 2020, contending that the government delayed the project.
  • The contracting officer denied the claim on May 6, 2020, stating she did not understand the claim and that Blanchard caused delays.
  • Blanchard filed a motion for summary judgment on August 12, 2020, including an amended claim.
  • The Navy filed a motion to dismiss Blanchard's drawing claim and second delay claim on October 7, 2020.

Parties

Appellant
Blanchard's Contracting, LLC
Respondent Agency
Navy
Contract Number
N40080-19-C-2026
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.