Shoreline Foundation, Inc.

November 17, 2023Judge O'Connell
Denied / Government PrevailedDelay / Disruption / SuspensionCDA Jurisdiction

Shoreline Foundation, Inc. appealed decisions related to delays and liquidated damages under Contract No. W912EP-16-C-0027. The Board granted the government's motion to dismiss part of the appeal for lack of jurisdiction.

Material Facts

  • USACE awarded Contract No. W912EP-16-C-0027 to Shoreline Foundation, Inc. on September 29, 2016.
  • The contract required the appellant to establish a 4.8-acre artificial reef off the coast of Brevard County, Florida.
  • A bid protest was filed by another contractor on October 6, 2016, which was resolved without changing the award.
  • Shoreline Foundation, Inc. submitted a request for equitable adjustment on November 15, 2017, seeking $237,882.60 and 54 days of delay related to the bid protest.
  • The Contracting Officer denied the REA on March 9, 2018, stating it was not a final decision.
  • On October 21, 2020, Shoreline Foundation, Inc. submitted a certified claim seeking $2,838,231 and a 245-day time extension.
  • The claim cited defective specifications and superior knowledge as causes of delays.
  • The Contracting Officer denied the claim on March 26, 2021, leading to the appeal docketed as ASBCA No. 62876.
  • A second final decision assessed liquidated damages of $249,690 due to delays beyond the revised completion date.

Parties

Appellant
Shoreline Foundation, Inc.
Respondent Agency
United States Army Corps of Engineers
Contract Number
W912EP-16-C-0027
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.