Group III Management, Inc. appealed a decision regarding compensable delay under a USACE contract for construction work, seeking an extension of the completion date and recovery of costs. The Board denied the government's motions to dismiss and for summary judgment.

Material Facts

  • USACE awarded Contract No. W912HN21C3008 to Group III for construction work at Seymour Johnson Air Force Base.
  • The contract was for a firm-fixed price of $4,883,000 and required completion within 365 days.
  • USACE issued a notice to proceed on December 8, 2021, setting a completion date of December 8, 2022.
  • Group III submitted a proposal for drainage-revision work on September 1, 2022, anticipating a 115-day time extension.
  • Modification No. P00003 was executed on February 22, 2023, increasing the contract price by $515,693 and extending the completion date by 115 days.
  • USACE assessed $63,252 in liquidated damages against Group III for late completion.
  • Group III submitted a request for equitable adjustment seeking $96,703 and an 84-day time extension.
  • USACE denied the REA, stating previous modifications included appropriate time and costs.

Parties

Appellant
Group III Mgt., Inc.
Respondent Agency
U.S. Army Engineer District, Savannah
Contract Number
W912HN21C3008
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.