B-424758

AADS Office Solutions International, LLC

Nov 24, 2026.Bureau of Indian AffairsDepartment of the Interior
DeniedSole-Source / Improper AwardPrice Reasonableness

GAO Digest

AADS Office Solutions International, LLC, of Phoenix, Arizona, protests the sole-source award of a $52,194.10 contract by the Department of the Interior, Bureau of Indian Affairs (BIA), to Interior Solutions, of Albuquerque, New Mexico, to provide and install a "Space Saver Filing System" for the purpose of securing sensitive tribal records. Protest at 1-4. AADS asserts that the agency failed to reasonably justify the award. We deny the protest.

Key Facts

Decision date
Nov 24, 2026.
Publicly released
Nov 25, 2026.
Agency
Bureau of Indian Affairs
Department
Department of the Interior
Decided by
Edda Emmanuelli Perez, General Counsel

Counsel

Protester
Quarles Law Firm
Eric J. Van Schyndle
Agency
Department of the Interior
James L. Weiner
GAO
Office of the General Counsel, GAO
Glenn G. Wolcott, April Y. Shields

Procurement

Instrument
Contract
Issued by
Department of the Interior
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: the grounded legal brief, semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Grounded AI Case Analysis

A verified legal brief: the holding, each protest ground with its determination, key amounts, cited authorities and practitioner takeaways, every quote checked against the decision text.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision15,868 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Authorities cited

3 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Federal Acquisition Regulation2
GAO Bid Protest Regulations1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

3 cases this decision cites, in the order it first names them. 2 of them open in this app; the rest are shown without a link because no published copy of them was confirmed.

American Sys. Corp.B-412501.2SageCare, Inc.B-411260Rochester Optical Mfg. Co.B-292137.2

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

AADS Office Solutions International, LLC, of Phoenix, Arizona, protests the sole-source award of a $52,194.10 contract by the Department of the Interior, Bureau of Indian Affairs (BIA), to Interior Solutions, of Albuquerque, New Mexico, to provide and install a "Space Saver Filing System" for the purpose of securing sensitive tribal records. Protest at 1-4. AADS asserts that the agency failed to reasonably justify the award.

Decision

Matter of: AADS Office Solutions International, LLC

File: B-424758

Date: November 24, 2026

Eric J. Van Schyndle, Esq., Quarles Law Firm, for the protester.

James L. Weiner, Esq., Department of the Interior, for the agency.

Glenn G. Wolcott, Esq., and April Y. Shields, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

Digest

Protest challenging agency's award of a sole-source contract using simplified acquisition procedures is denied where the record shows that the agency reasonably justified the award on the basis of urgency.

Decision

AADS Office Solutions International, LLC, of Phoenix, Arizona, protests the sole-source award of a $52,194.10 contract by the Department of the Interior, Bureau of Indian Affairs (BIA), to Interior Solutions, of Albuquerque, New Mexico, to provide and install a “Space Saver Filing System” for the purpose of securing sensitive tribal records. Protest at 1-4. AADS asserts that the agency failed to reasonably justify the award.

The page numbers referenced in this decision are the PDF page numbers for the various pleadings and documents submitted.

We deny the protest.

BACKGROUND

In March 2026, BIA representatives participated in an onsite visit to the Navajo Nation Tribal Enrollment (NNTE) program's tribally owned facility in Crown Point, New Mexico to “evaluate records, equipment, and facility conditions.” First Decl. of Acting Branch Manager at 1. Among other things, the BIA found that: the facility “lacks proper heating and cooling” and “only provides cold water”; “there are visible water leak stains on the office ceilings”; “[t]he entrance door is broken and cracked”; and “[e]lectrical extension cords are running through the hallways.” Req. for Dismissal, attach. A, Memorandum at 1. Additionally, the agency noted that: the NNTE program “manages sensitive, personally identifiable information (PII) for Navajo Nation citizens,” Req. for Dismissal at 2; the facility contained a large volume of “paper-only tribal trust data requiring secure storage and controlled access,” First Decl. of Acting Branch Manager at 2; and the sensitive records were being stored in various unsecured containers. Id. Accordingly, the agency concluded there was an immediate need for “a high-capacity, space-efficient[,] records-storage solution such as a Spacesaver or Lektriever system to securely store NNTE records.” Id. at 1; see Req. for Dismissal at 3‑4.

More specifically, the records were being stored in “23 filing cabinets, 5 small FireKing cabinets (two-drawer type), 14 additional cabinets with shelving containing reference materials and/or enrollment records, one large box of family records, and approximately 20 cubic feet of original base roll records.” First Decl. of Acting Branch Manager at 2.

Based on BIA's site visit, efforts were initiated in April 2026 to relocate the NNTE program activities to a BIA-owned facility and to obtain a secure storage system for the NNTE records. Req. for Dismissal at 1-2. In this context, a “[r]ecords [r]epresentative with the Bureau of Trust Funds Administration recommended Interior Solutions based on his experience with Spacesaver systems.” First Decl. of Acting Branch Manager at 1; Req. for Dismissal at 3. Thereafter, the agency conducted market research by seeking a quotation from Interior Systems and contacting two other companies to determine whether they could meet the agency's needs. Specifically, the agency states that the acting branch manager “contacted Global Industrial and Nationwide and was informed that while each could ship storage units, assembly and installation would be [BIA's] responsibility.” First Decl. of Acting Branch Manager at 1. The agency further determined that “ordering and installing the storage system would take an estimated 8‑10 weeks.” Id. at 3. Accordingly, the agency concluded that awarding a contract for a secure record storage system constituted an urgent requirement and, based on its market research, concluded that Interior Systems was the only vendor capable of meeting that requirement within a timeframe that would shortly follow the pending relocation.

The acting branch manager further states that she “attempted to contact Native Vet Material, but received no response.” Id. at 1.

The agency notes that, although relocation of the NNTE staff and records was “an urgent operational and safety matter,” the relocation “could not occur immediately because the receiving space first had to meet obligations for safety, accessibility, records protection, labor-relations compliance, and procurement approvals, and the parties had to finalize revocable license terms governing non-federal use of BIA property.” Second Decl. of Acting Branch Manager at 3. For example, BIA “initiated union notification on May 26, 2026, with union response on June 24, 2026, seeking clarification and resolution of employee concerns.” Id. at 5. The agency acknowledges that installation of the record storage system was not scheduled to occur until approximately 10 weeks after relocation of the staff occurred. Id. at 2.

On August 5, the agency posted a notice on SAM.gov (System for Award Management) stating its intent to award the contract at issue here to Interior Systems on a sole-source basis. Protest, exh. A, Notice of Intent to Award Sole Source Contract. On August 6, the contracting officer executed a document justifying that action. Req. for Dismissal, attach. D, Single Source Determination and Findings (D&F). Among other things, the D&F stated:

Although the D&F refers to “FAR [Federal Acquisition Regulation] 12.102(a)” as the authority for this determination, see Req. for Dismissal, attach. D, Single Source D&F at 1, agency counsel explains that the contracting officer “completed [the D&F] under the Simplified Acquisition Threshold pursuant to Revolutionary FAR Overhaul [(RFO)] 12.102(a), concluding that urgent circumstances made only one source reasonably available.” Req. for Dismissal at 2, 3 n.3 (explaining that the agency has adopted the RFO part 12 deviation).

[A]cquiring a secure records management system aligns with federal priorities for safeguarding government property and protecting personally identifiable information, in accordance with statutory responsibilities. . . . Without secure records storage, sensitive data remains at risk of loss, damage, or unauthorized access, jeopardizing federal trust responsibilities and records management obligations. Further delays would disrupt operational continuity, as unsafe facility conditions impede mission support. Awarding this action is therefore crucial for restoring safe operations, protecting federal and tribal records, and ensuring uninterrupted service to the Navajo Nation.

Id. at 2.

On August 6, the agency awarded the contract to Interior Solutions in the amount of $52,194.10. Protest, exh. B, Notice of Award. That same day, AADS sent an email to the contracting officer expressing an interest in competing for the requirement. Protest, exh. C, Email Chain at 3. On August 7, the agency posted the notice of award on SAM.gov, and separately advised AADS by email that “[the contract] has been awarded.” Id. at 2; see Protest, exh. B, Notice of Award.

On August 13, AADS filed an agency-level protest requesting that the agency “review the circumstances surrounding this award, including the timing of the solicitation, AADS's timely response, and the decision to award the contract as a sole source prior to allowing AADS an opportunity to submit a competitive bid.” Protest, exh. D, Agency Protest at 1. On August 19, the contracting officer issued a decision stating, “I dismiss the protest for failure to provide a ‘[d]etailed statement of the legal and factual grounds for the protest,'” but added, “[i]n the alternative, I deny the protest on the merits on the basis that [the agency] appropriately awarded the Contract to [the] Awardee on a sole source basis.” Protest, exh. E, Decision on Agency Protest at 4. On August 21, AADS filed this protest with our Office.

DISCUSSION

AADS protests that “[the agency's] sole-source determination was unreasonable because the agency did not establish that only one source was reasonably available.” Protest at 4. In this context, AADS does not dispute the necessity of securing NNTE records; rather, AADS asserts that, upon receipt of AADS's August 6 email identifying AADS as a potential vendor, the agency was obligated to delay the acquisition by seeking further information from AADS. Id. Additionally, AADS criticizes the extent of the agency's market research, complaining that it failed to research the specific storage system that AADS markets. Id. at 1-2; Protester's Resp. to Req. for Dismissal at 3‑6.

AADS asserts the agency “did not make the award until August 7 at 1:32 p.m.” Protest at 2. To the contrary, the record states that the contract was awarded on August 6. Protest, exh. B, Notice of Award at 2. The record does not establish whether the contract was awarded before or after receipt of AADS's August 6 email.

The agency responds that, even assuming it could have delayed the award to accommodate AADS's request, its actions in moving forward with the sole-source award were reasonable in light of the urgent circumstances related to both the pending office move and the sensitivity of the unsecured documents. Agency Reply to Protester's Resp. to Req. for Dismissal at 3. Specifically, in addition to the need to relocate NNTE staff, the agency notes the urgent requirement to meet its statutory obligations regarding protection of NNTE's records. Req. for Dismissal at 5-6. The agency further maintains that it conducted reasonable market research by obtaining a quotation from the awardee, who was known to have installed similar systems, as well as engaging in attempts to identify alternative vendors--but determined that the alternative vendors it identified were unable to meet the agency's requirements. Id. Finally, the agency notes that it reasonably determined that installation of a secure record storage system would require eight to ten weeks of lead time for ordering and delivery of materials and supplies and, accordingly, concluded that further delays would be detrimental to meeting its obligation to secure the NNTE records. Id.; Second Decl. of Acting Branch Manager at 2; Req. for Dismissal, attach. D, Single Source D&F at 2.

In this regard, the agency refers to the Indian Self-Determination and Education Assistance Act, 25 U.S.C. § 5301 et seq. Req. for Dismissal at 2. As noted above, AADS has not disputed the statutory requirement to protect NNTE records.

When conducting a procurement utilizing simplified acquisition procedures, contracting officers are only required to obtain competition to the “maximum extent practicable,” and we will not object to a sole-source award in a simplified acquisition unless the agency acted unreasonably. 41 U.S.C. § 3305(d); RFO 12.201(c); see also FAR 13.104; Information Ventures, Inc., B‑290785, Aug. 26, 2002, at 3. More specifically, a contracting officer may solicit from a single source if the contracting officer determines that only one source is available and documents the basis for that decision. RFO 12.102(a); see also FAR 13.106-1(b)(1)(i); American Sys. Corp., B-412501.2, B‑412501.3, Mar. 18, 2016, at 8-9; SageCare, Inc., B-411260, June 23, 2015, at 3. In this context, we have found that urgent operational requirements may justify limiting competition even when an alternative vendor claims capability. Summit Techs., Inc., B‑419126, B‑419126.2, Nov. 19, 2020, at 5. Finally, as noted above, we review an agency's decision to limit competition in simplified acquisitions under a reasonableness standard. See Information Ventures, Inc., supra; Critical Process Filtration, Inc., B‑400746 et al., Jan. 22, 2009, at 5.

As noted above, the agency states that it made the sole-source determination at issue here pursuant to RFO part 12, which replaces certain FAR part 13 provisions regarding simplified acquisition procedures. More specifically, while FAR provision 13.106-1(b)(i) identifies “urgency” as one of the bases for restricting competition to a single source, RFO provision 12.102(a) simply provides that, in such restriction of competition, an agency need only “document [its] decision that only one source is available and the basis for [its] decision.” The parties have not alleged or established that any distinction between the prior FAR and RFO affect the analysis of the agency's actions in this procurement.

Based on our review of the record here, we reject AADS's assertions that the agency's assessment of urgency, the scope of its market research, and its resulting determination to make a sole-source award to Interior Systems were unreasonable. First, as noted above, in conducting a procurement under simplified acquisition procedures, an agency need only obtain competition to the “maximum extent practicable” taking into consideration the specific circumstances presented in each procurement, including an assessment of urgency.

Here, in our view, the record supports the agency's determination that both the condition of the prior facility and methods by which records were being stored at that facility, created urgent requirements for the agency to take various actions--including relocation of the NNTE staff and records, along with acquisition of a secure storage system. As noted above, the agency was concerned that further delay would expose the NNTE's sensitive data to an ongoing risk of loss, damage, or unauthorized access. In this regard, AADS's opinion that the acquisition could have been delayed further to accommodate AADS, and its disagreement with the agency's judgment in that regard, does not render the agency's judgment unreasonable.

We similarly reject AADS's expressions of dissatisfaction regarding the extent of the agency's market research. Here, the contracting officer was aware that its record storage requirements could be met using alternative products “such as a Spacesaver or Lektriever system,” see First Decl. of Acting Branch Manager at 1, and considered alternative potential sources to meet those requirements. We are unpersuaded that the agency's failure to consider the specific product marketed by AADS rendered the market research unreasonable. Accordingly, under the circumstances presented here, we find the agency's market research efforts to be adequate and, therefore, reasonable. In short, we have considered all of AADS's various complaints and find no merit in them.

As noted above, AADS's August 21 protest to our Office was filed within 10 days after the agency rejected AADS's agency-level protest; accordingly, the issues raised in the agency-level protest are timely under our Bid Protest Regulations. 4 C.F.R. § 21.2(a)(3). Nonetheless, in its protest to our Office, AADS, for the first time, challenges the agency's price reasonableness determination. Protest at 4. Since AADS was advised of the contract price no later than August 7, and its agency-level protest did not raise this issue, that portion of its protest is dismissed as untimely filed. See, e.g., Rochester Optical Mfg. Co., B-292137.2, Mar. 16, 2004, at 4 n.3.

The protest is denied.

Edda Emmanuelli Perez

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Protest Ground

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.