GAO upholds the Navy's Salary.com labor rate adjustments

HII Mission Technologies Corporation (HII MTC) proposed $28.2 million less than Amentum Services, Inc. for the Navy Integrated Training Environment (NITE II) task order and still lost on cost. After the Navy's cost realism adjustments, including labor rates it checked against Salary.com, HII MTC's evaluated cost rose by $156.4 million and finished $12.8 million above Amentum's. On November 5, 2026, the Government Accountability Office denied the protest in B-424692, which it released on November 16, 2026.

If you price cost-type work, an agency can test your rates against a salary database you do not control, and GAO will defer to it when your own data is something the agency cannot see. Below are the four points to take into your next cost volume. Read the full decision on GAO's website.

1The cost evaluationYour lower price can become the higher evaluated cost

One term first. A cost realism analysis asks whether the costs you propose are realistic for the work, and on a cost-reimbursement award the agency replaces costs it finds too low with its own estimate. The RFP said the Navy would adjust upward any costs it considered unrealistically low.

HII MTC proposed $679,709,811 against Amentum's $707,945,501. As evaluated, HII MTC came to $836,071,898 and Amentum to $823,307,623: an upward adjustment of 23 percent for HII MTC and 16 percent for Amentum. With Amentum also rated Outstanding to HII MTC's Good on the technical factor, the source selection authority found that Amentum "represents a clear and unambiguous better value over HII MTC".

2Basis of estimateSalary.com beat the company's own pay data

The RFP told offerors to "provide substantiating information that fully corroborates each direct labor rate proposed", and reserved the Navy's right to look beyond the proposal, naming "salary databases or websites, invoices, aggregated cost data, historical data" among the sources. For positions with no named candidate, which the RFP calls TBD, the Navy compared proposed rates to Salary.com.

HII MTC priced those positions from its internal job code system, built from several national salary surveys. The Navy had no access to that system and relied instead on "verifiable Salary.com labor categories and rates". GAO found that reasonable "given the greater insight to the rates that the Salary.com data afforded the agency as compared to the CJCS rates used by the protester". The rule it applied comes from CSI, Inc. (2015):

"an agency may reasonably adjust an offeror's proposed labor rates where the offeror fails to provide adequate detail to support its rates, and where the agency relies on reasonable sources of data to support its adjustments"

GAO reviews a realism analysis under FAR 15.404-1 and FAR 15.305, and asks for a reasonable measure of confidence, not scientific certainty. Of the 5,960 GAO decisions GovConDash holds in full text, 55 mention Salary.com, and you can search all of them in the GAO Protests tab.

Agencies also check rates against two public sources: Bureau of Labor Statistics wage data and GSA's CALC+ tool. Across all 5,960 GAO decisions, the Bureau of Labor Statistics comes up in 68, and CALC+ or its predecessor, CALC, in 8. In Herren Associates (2024), the Navy's solicitation said it would test the cost realism of every proposed employee against BLS direct labor rates for the local area. In OBX-MCR Alliance (2025), GSA checked the awardee's rates against CALC+ prices paid data and BLS rates, and GAO noted that its decisions have consistently accepted GSA's CALC tools as part of a price analysis. As GAO read the tool's user guide, an agency "should not rely mechanically or solely on the tool to establish price reasonableness". Anyone can use BLS wage data and CALC+, so check your rates against both before you submit.

3The 50th percentileThe 50th percentile is the Navy's default

The Navy used the 50th percentile for most labor categories because, in the cost analyst's words, "the 50th percentile establishes a realistic baseline as it represents the middle of the market". HII MTC had used a different percentile, which GAO redacted. That "percentile metric does not exist within the Salary.com database", the analyst explained.

Where no Salary.com category matched, the analyst picked the closest description with the technical point of contact and recorded each match. Site leads and site managers both mapped to one Salary.com position, so the Navy priced site leads at the 25th percentile and site managers at the 50th to reflect their different education and experience requirements. GAO found that reasonable.

4Geographic adjustmentsDo not stack a geographic discount on local data

The RFP reserved the right to "adjust direct labor rates upward in its cost realism evaluation to reflect prevailing rates in the performance location, regardless of personnel's intent to relocate, telework". HII MTC lowered its TBD rates with geographic factors; the evaluators found that "applying a blanket geographic discount to TBD positions fails to account for the premium national market rates commanded by specialized, cleared personnel".

The Navy's Salary.com rates were already set for the performance locations, so applying HII MTC's factors as well would have been a "double discount". GAO agreed, and upheld the same adjustments to HII MTC's subcontractors.

GAO also denied HII MTC's technical and past performance grounds. Even a better past performance rating would have left HII MTC lower rated and higher in cost, so it could show no prejudice.

Bottom line

GAO let the Navy replace rates built on HII MTC's internal job code system with Salary.com data at the 50th percentile. Labor rates were among the Navy's cost realism adjustments, and after them HII MTC's lower proposed cost became the higher evaluated cost. When an agency cannot see how your rates were built, expect it to substitute a source it can check, and expect GAO to defer to that choice.

Documents and data used in this piece

The decision

The decision GAO relied on

Other labor rate benchmarks

The regulations

Disclaimer. This piece is commentary on a published decision. It is not legal advice, and it is not a determination about any contractor, cost or contract. Confirm how the decision applies to you with counsel or a government contracts professional. GAO issued the decision under a protective order and released a redacted version, which withholds the percentile HII MTC proposed and the range of its geographic factors, so this piece does not state them. Read GAO's decision in full.

GovConDash.ai

See how GAO has treated labor rates before you price yours

Start a 14-day free trial of Pro and open the GAO Protests tab: search the full text of every decision for Salary.com, cost realism and the labor categories you bid. Checkout takes a card and charges nothing for 14 days. Cancel before then and you pay nothing; keep going and it becomes $99 / month. One trial per account.

Keep reading

MAS Refresh #34 Brings GSA's AI Clause. Here Is What It Requires.

A GSA schedule change read for the contractor: what GSA's new clause for orders that buy an LLM requires of MAS holders, and the deadlines it sets.