Class Deviation 2027-O0001: What Changed in the DFARS Accounting System Criteria

Under the new clause, your accounting system is measured against six criteria, not eighteen. Class Deviation 2027-O0001, issued on November 18, 2026 and effective immediately, rewrites DFARS 252.242-7999, Accounting System Administration: the March clause listed eighteen criteria in paragraph (c), and the November clause lists six in paragraph (e), after a lead-in that asks for a sound internal control environment that adheres with GAAP. Nine of the eighteen have no counterpart among the six.

Paragraph (c) now holds something else: the conditions under which a contractor may have an independent public accountant audit the system. DCAA's accounting system audit programs, both dated September 2026, still test all eighteen criteria by their (c) numbers. Below: what the six keep, what they leave out, the new audit path, and what has not changed.

Defense Pricing, Contracting, and Acquisition PolicyIssued November 18, 2026, effective immediately

Class Deviation 2027-O0001

Streamlining Contractor Business Systems

  • What it replaces: the DFARS subpart 242.75 text and the 252.242-7999 clause of Class Deviation 2026-O0050, dated March 6, 2026, along with the estimating, earned value, purchasing and property system texts of other deviations.
  • Signed by: John M. Tenaglia, Principal Director, Defense Pricing, Contracting, and Acquisition Policy.
  • What it implements: the Deputy Secretary of War memorandum "Fostering One Strong Industrial Base," dated September 14, 2026, and Line of Effort #10, Common Sense Accounting, Reliance on Commercially Accepted Practices of the Acquisition Transformation Strategy.
  • How long: until the text is incorporated into the DFARS or the deviation is rescinded.

The short version

  1. 1Six criteria replace eighteen. The six keep the segregation of direct, indirect and preproduction costs, accumulation by contract, indirect allocation, ledger adjustments, unallowable costs and billings. Timekeeping, labor distribution, general ledger control and reconciliation, internal audits and monthly cost determination are not stated.
  2. 2The criteria moved to paragraph (e). Paragraph (c) is now the independent public accountant option and (d) a single audit under government auditing standards, by the Government or by an accountant the contractor chooses.
  3. 3An audit now needs a trigger. $100 million in qualifying contracts in the prior fiscal year, a risk assessment, or the contractor's own request. The clause stays out of contracts with nontraditional defense contractors.
  4. 4DCAA's programs still test the eighteen. 17741ST and 11070ST predate the deviation and cite every criterion by its old (c) number, and the deviation does not relieve existing material weaknesses. GovConDash's Audit Readiness tab already cites the deviation on its DoD Accounting System audit row.

1DFARS 252.242-7999(e), System criteriaEighteen criteria become six

The March clause, in Class Deviation 2026-O0050, told the contractor its accounting system "shall provide for" eighteen things, from a sound control environment to accounting practices that follow the Cost Accounting Standards Board's standards or GAAP. Those eighteen are word for word the criteria of the codified DFARS 252.242-7006, which the eCFR still prints in its Jan 2025 version.

The November clause opens differently. The system must "ensure a sound internal control environment that adheres with GAAP", and it must ensure six things:

DFARS 252.242-7999(e) under Class Deviation 2027-O0001

  1. (e)

    Internal control environment that adheres with GAAP

    "The Contractor's accounting system must ensure a sound internal control environment that adheres with GAAP"

    Carries March criteria (c)(1) and (c)(18)

  2. (e)(1)

    Direct, indirect and preproduction costs segregated

    "Direct costs are classified and segregated from indirect costs, and preproduction costs (nonrecurring/startup) are distinctly segregated from production costs, in accordance with the contract terms, as applicable"

    Carries March criteria (c)(2) and (c)(14)

  3. (e)(2)

    Direct costs accumulated by contract

    "Direct costs are identified and accumulated by contract, as applicable"

    Carries March criterion (c)(3)

  4. (e)(3)

    Indirect costs allocated by documented methods

    "Indirect costs are accumulated and allocated to contracts using documented methods that are consistent with the contract terms, as applicable"

    Carries March criterion (c)(4)

  5. (e)(4)

    Every ledger adjustment has a documented business purpose

    "Each adjustment to the general ledger, subsidiary ledgers, or other information systems that affects direct and indirect contract costs, including adjusting journal entries, reclassifications, and cost transfers, has a documented business purpose"

    Carries March criterion (c)(7)

  6. (e)(5)

    Unallowable costs identified and accumulated

    "Unallowable costs are identified and accumulated"

    Carries March criterion (c)(12)

  7. (e)(6)

    Billings prepared in accordance with contract terms

    "Billings are prepared in accordance with contract terms"

    Carries March criterion (c)(16)

Read the eighteen against the six and they fall into three groups. Six keep their subject in a November criterion, often in different words. Three are carried in part: the control environment loses its accounting framework and organizational structure, billings no longer have to reconcile to the cost accounts, and GAAP stays while the Cost Accounting Standards Board drops out of the text. Nine have no counterpart at all.

The eighteen March criteria, and where each went

(c)(1)

Internal control environment and organization

March 2026 clause, paragraph (c)
"A sound internal control environment, accounting framework, and organizational structure"
November 2026 clause (e)
"The Contractor's accounting system must ensure a sound internal control environment that adheres with GAAP"
Terms the November clause never uses
accounting frameworkorganizational structure
Tap or hover a criterion for both texts. A criterion is carried when a phrase of it appears in one of the November criteria; a term listed as never used was counted and does not appear anywhere in the November clause. The grouping is our reading of the two texts.

The words change even where the subject stays. Adjusting entries used to need approval and documentation; now every adjustment to the general ledger, subsidiary ledgers or other systems that affects contract costs, reclassifications and cost transfers included, needs a documented business purpose. Indirect costs used to need a logical and consistent method; now they need documented methods consistent with the contract terms.

2What the six leave outNine criteria with no counterpart

Most of the criteria with nothing in the November clause are about how costs are recorded and checked: costs under general ledger control ((c)(5)), subsidiary ledgers reconciled to the general ledger ((c)(6)), management reviews or internal audits ((c)(8)), timekeeping by cost objective ((c)(9)), labor distribution ((c)(10)), monthly determination of contract costs ((c)(11)), costs by contract line item and unit ((c)(13)), cost information for the cost and funds clauses ((c)(15)), and data for pricing follow-on acquisitions ((c)(17)). None of their key terms, from timekeeping to follow-on, appears anywhere in the new clause.

The contract clauses these criteria supported remain in force. Criterion (c)(15) existed to serve the limitation of cost, limitation of funds and allowable cost and payment clauses, and those clauses stay in a cost type contract on their own terms. A timekeeping system that cannot support a voucher is still a problem at the billing stage. What changes is that a weakness there is no longer, by itself, a failure to meet a stated system criterion of 252.242-7999.

3DFARS 252.242-7999(c) and (d)An independent public accountant can now audit the system

The November clause keeps the March clause's paragraphs and adds two in the middle, so everything from the criteria on moves down two letters. The new definition section also adds one sentence: "Accounting systems may be stand-alone systems or integrated with other systems."

DFARS 252.242-7999, paragraph by paragraph

November 2026 (2027-O0001)

March 2026 (2026-O0050)

Tap or hover a paragraph to see where it came from or where it went. Headings are the clauses' own; the one-line descriptions are ours.

Paragraph (c) sets the condition. A contractor that has a "registered independent public accounting firm perform an audit resulting in an unqualified GAAP financial statement audit opinion with no reported material weaknesses in internal controls impacting Government contracts" may choose how this business system is audited. Paragraph (d) then makes the accounting, estimating and material management accounting system audits a single audit, conducted under "Generally Accepted Government Auditing Standards (GAGAS) for attestation examination engagements certifying compliance with the system criteria".

A contractor that does not meet the condition gets one consolidated Government audit. One that does may choose, within 30 days of the contracting officer saying an audit is necessary, between the Government and an independent public accountant it engages. The accountant's report goes straight to the contracting officer, with a copy to the cognizant auditor, and "The Government will rely on an unmodified GAGAS audit report."

Read the new paragraph letters carefully. The subpart's own definition at DFARS 242.7501 still points to the system criteria in paragraph (c) of 252.242-7999, while the clause's definition points to paragraph (e). The criteria are in (e).

4DFARS 242.7503 and 242.7504An audit now needs a trigger

The March subpart said nothing about when an accounting system is audited. The November subpart adds a section that does: the system is subject to audit when the contractor had $100 million in cost type, incentive, time-and-materials, labor-hour or progress payment contracts in its preceding fiscal year; when the head of the contracting activity "determines an accounting system audit is needed based on a risk assessment of the contractor's experience and system vulnerability"; or when the contractor needs an approved system to bid on flexibly priced contracts under FAR 16.301-3.

The audit path under Class Deviation 2027-O0001

The deviation's words

"determines an accounting system audit is needed based on a risk assessment of the contractor's experience and system vulnerability"

Class Deviation 2027-O0001, subpart 242.75

Tap or hover a step for the deviation's own words. Section labels follow the deviation's numbering.

The prescription narrows too. The clause goes into cost type, incentive, time-and-materials, labor-hour and progress payment contracts, "except for contracts with nontraditional defense contractors". The March prescription had no such exception.

5Nontraditional defense contractorsOutside every business system clause

Under the November deviation, a nontraditional defense contractor is not subject to the accounting system clause, the contractor business systems clause, the material management and accounting system rules, or earned value management. Each exclusion is in the deviation's own words:

What Class Deviation 2027-O0001 leaves out of their contracts

Accounting system clause, DFARS 252.242-7999
"Insert the clause at 252.242-7999, Accounting System Administration, in solicitations and contracts, except for contracts with nontraditional defense contractors"
DFARS 242.7504
Contractor business systems clause, DFARS 252.242-7998 (the payment withholds)
"Insert the clause at 252.242-7998, Contractor Business Systems, in solicitations and contracts (other than in contracts with nontraditional defense contractors ..."
DFARS 242.7001
Material management and accounting system rules
"Do not apply to small businesses, nontraditional defense contractors, educational institutions, or nonprofit organizations."
DFARS 242.7200(b)(2)
Earned value management
"Exemptions. (1) General. Do not apply this subpart to contracts" ... "Awarded to nontraditional defense contractors."
DFARS 234.201-70(j)(1)
Unless the exemption is waived
"may waive the exemption relating to nontraditional defense contractors by written determination that applying the requirement for an earned value management system to a nontraditional defense contractor is in the best interest of DoD"
DFARS 234.201-70(j)(2)

In practice, that means a nontraditional defense contractor's contracts carry no accounting system criteria, no approval or disapproval of its system under 252.242-7999, and no payment withholds under 252.242-7998. None of these exclusions is in the March text, which never uses the word nontraditional. The deviation's earned value notice provision names where the term is defined: "This provision does not apply to nontraditional defense contractors, as defined in Defense Federal Acquisition Regulation Supplement 202.101."

The exclusion does not remove the accounting system requirement for a cost type contract. FAR 16.301-3 says "A cost-reimbursement contract may be used only when" several conditions are met, and one of them is "The contractor's accounting system is adequate for determining costs applicable to the contract or order". A nontraditional defense contractor that wants a cost-reimbursement contract still needs an accounting system the contracting officer can find adequate.

The audit section does not exempt it either. One of the triggers in DFARS 242.7503 is the contractor's own need for an approved system: "The contractor requires an audit to approve their system for compliance with FAR 16.301-3 to be eligible to bid on flexibly priced contracts." Unlike 242.7504, that section never mentions nontraditional defense contractors.

All of this depends on whether your company meets the definition. DFARS 202.101 defines a nontraditional defense contractor as "an entity that is not currently performing and has not performed any contract or subcontract for DoD that is subject to full coverage under the cost accounting standards prescribed pursuant to 41 U.S.C. 1502 and the regulations implementing such section, for at least the 1-year period preceding the solicitation of sources by DoD for the procurement". The cost accounting standards it refers to are those of 41 U.S.C. 1502, and the definition itself is the statute's, at 10 U.S.C. 3014. We walk through the definition in Are You a Nontraditional Defense Contractor? DCAA Will Now Check.

Check a company against the definition

Check nontraditional defense contractor status under 10 U.S.C. 3014. GovConDash's NDC Status page reads a company's registration and its Department of War awards.

Open NDC Status

6DCAA audit programs 17741ST and 11070STDCAA's programs still test the eighteen

DCAA audits an accounting system with 11070ST, Accounting System Audit, version 4.5, and at nonmajor contractors with 17741ST, Post Award Accounting System Audit at Nonmajor Contractors, version 7.6. Both are dated September 2026, before the deviation, and neither names it. Both test all eighteen March criteria, and both cite each one by its paragraph (c) number, from 252.242-7999(c)(1) through (c)(18).

In the November clause those numbers point somewhere else. Paragraph (c) is now the accountant paragraph, the billing criterion the programs cite as (c)(16) is now (e)(6) without the reconciliation to the cost accounts, and nine of the criteria the programs test are not stated at all.

For a contractor, the practical question is which clause your contract carries. One bullet of the deviation reads: "Modify existing solicitations and contracts to implement the attached solicitation provisions and contract clauses as soon as practicable". Until that happens, a contract may carry the codified 252.242-7006, the March clause or the November one. When an audit finding cites a 252.242-7999(c) criterion, check it against the clause in your contract, and ask which of the six it maps to if your contract has been modified.

7DFARS 252.242-7999(f) to (h)What did not change

The material weakness definition is the same, word for word. So is the process: the contracting officer makes an initial determination, you respond within 30 days, and after a final determination you correct the weaknesses or submit an acceptable corrective action plan within 45 days. Payments are still withheld under 252.242-7998 when the system is disapproved and the contract carries that clause. The codified 252.242-7006 points to DFARS 252.242-7005 for the same withholding.

And the slate is not wiped clean. Among its instructions to contracting officers, the deviation lists this one: "Not relieve contractors from resolving existing material weaknesses or completing corrective actions under an existing contract".

Key takeaways

  • Map your controls to the six. Segregation, accumulation by contract, documented allocation methods, a business purpose for every adjustment, unallowable costs and billings under contract terms are the stated criteria now.
  • Keep the records the eighteen required. Timekeeping, labor distribution and reconciliations still support your vouchers and your incurred cost submission, and DCAA's current programs still test them.
  • Check whether you qualify for the accountant pathway. It needs an unqualified GAAP opinion with no reported material weaknesses affecting Government contracts, and you choose within 30 days of being told an audit is necessary.
  • Know whether you will be audited at all. Below $100 million in qualifying contracts, an audit comes from a risk assessment or from your own request to bid on flexibly priced work.
  • Confirm your status as a nontraditional defense contractor. It keeps the accounting, business systems and material management clauses out of your contracts and exempts you from earned value management unless the exemption is waived. Your accounting system still has to be adequate for a cost type contract.
  • Read every cite against the clause in your contract. A 252.242-7999(c) number means a criterion in the March clause and the accountant paragraph in the November one.

Documents and data used in this piece

The class deviations

The regulations

DCAA audit programs

On GovConDash

Disclaimer. This piece is commentary on a DoW class deviation, the clause it replaces and two DCAA audit programs. It is not legal advice, and it is not a determination about any contractor, contract or accounting system. Confirm which clause your contracts carry and how it applies to you with counsel or a government contracts professional. Read the deviation in full.

GovConDash.ai

See which audit programs point at your system

Start a 14-day free trial of Pro and keep the DCAA audit programs, the class deviations and your own audit readiness profile in one place. Checkout takes a card and charges nothing for 14 days. Cancel before then and you pay nothing; keep going and it becomes $99 / month. One trial per account.

Keep reading

Are You a Nontraditional Defense Contractor? DCAA Will Now Check.

What qualifies a company as a nontraditional defense contractor, the status that keeps the business system clauses out of its contracts.